Work on Hospital City project still moving slowly

The government has spent $240 million on the project so far.

Spanish version

Temas:

Social Security Director Estivenson Giron said work on the Hospital City project will fully resume in March, but recognized that work is currently going along very slowly.

Giron confirmed that the firm has been paid $240 million so far for the project.

Negotiations with the firm FCC have not been finalized as the two sides are at odds over several points, including the material that is going to be used in interior walls.

Ministry of Health official Temístocles Díaz said the most contentious issue has been the material to be used for the walls. The contractor wants to use drywall, but that has been rejected by the government based on opinions that it is not suitable due to the risk of contamination by bacteria. The ministry is demanding the contractor use concrete.

Ulises Lay, a member of the Panamanian Society of Engineers and Architects, said that the drywall is a precast material that "is not an option for use in the construction of hospitals. The best material for this type of structure will always be concrete."

Work was supposed to fully resume on the project on Jan. 15. That would mean about 2,000 workers would be on the site. But there are currently less than 200 workers there.

Giron said that it will be fully up to speed in March. The project is about 45 percent finished. Its budget is $517 million. 

Comentarios

Los comentarios son responsabilidad de cada autor que expresa libremente su opinión y no de Editorial por la Democracia, S.A.

Por si te lo perdiste

Sociedad Empieza demolición de la cárcel pública de David

Las autoridades dijeron que tenían identificados a los autores del siniestro.
Especial para La Prensa/Flor Bocharel Q.

Última hora

Pon este widget en tu web

Configura tu widget

Copia el código

Directorio de Comercios

Lo último en La Prensa

Canal ampliado 99% de avance en trabajos en esclusas

Más de 2 mil tránsitos en 15 meses de operación. Más de 2 mil tránsitos en 15 meses de operación.
Más de 2 mil tránsitos en 15 meses de operación. LA PRENSA/Archivo

Los trabajos menores y defectos pendientes en el tercer juego de esclusas que desarrolla el contratista Grupo Unidos por el ...

SEGURIDAD EN NAVEGACIÓN 121 actos de piratería

Infografía Infografía
Infografía LA PRENSA

Entre enero y septiembre se han registrado 121 incidentes de piratería y robo a mano armada contra buques en distintas partes ...

negocios Cinco SEM se instalarán en el país

Visa es una de las 12 firmas aprobadas este año. Visa es una de las 12 firmas aprobadas este año.
Visa es una de las 12 firmas aprobadas este año.

Las estadounidenses Visa y McKinsey & Company, Inc., y la suiza Panalpina World Transport, son algunas de las firmas que ...